Planning before plans
John D. McGregor, Clemson University and Luminary Software
LLC, U.S.A.
|
 |
COLUMN

PDF Version |
Abstract
A plan is a blueprint for solving a problem. It summarizes the decisions
that have been made during the planning of that solution. In this
month’s issue of Strategic Software Engineering, I want to
talk about the strategic importance of planning in making plans.
1 INTRODUCTION
The television schedule is full of so called reality shows where otherwise
reasonably sensible people do ridiculous things to win prizes. In software
development we see the same phenomenon when otherwise sensible professionals
write plans, without doing any planning, just to meet a deadline. I
have encountered this many times but it never fails to amaze me. This
is a direct result of deliverable-driven processes. These processes
reward creating the document because it is measurable and tangible
as opposed to rewarding the thought that goes into planning which is
much less tangible.
Answers.com says a plan is: “A scheme, program,
or method worked out beforehand for the accomplishment of an objective”. “Worked
out” is my focus this month. A plan is worked out by specific
actions and decisions that go before the actual writing down of specific
actions. When a plan is written before the method for accomplishing
a task is “worked out,” decisions are made implicitly without
sufficient analysis of the trade-offs that are almost always required
for an effective plan.
Effective is the key word. I don’t have some theoretical objection
to plans made without appropriate planning. They just aren’t
as effective. How can we know this? By autopsying failures. Often by
tracing back we find that plans that fail do so because of factors
that were present and knowable prior to the plan being executed. That
is a faulty plan and one that could have been effective if there had
been sufficient planning.
Planning is defined to be “an act of formulating a program
for a definite course of action.” There are specific actions
that occur during planning that lead to a better plan than those produced
by off-the-cuff writing. I will get into those actions later. For now,
it is sufficient to say that writing a plan should be preceded by formulating
a course of action.
Developing a software intensive product is a complex endeavor
that requires much planning and a number of plans. Management plans
include
resource allocations, development schedules and release plans. Technical
plans include architectures, test plans, configuration management plans
and quality assurance plans.
What is needed is a very efficient planning process. Some agile methods
do this by having very short term plans such as planning for a 24 hour
period during the daily Scrum or for a 30 day Sprint [Schwaber 02].
Their hypothesis is that plans of longer duration have to be revised
anyway because of the constant churn in a development project so shorter
plans involve less waste of time. Indeed I have observed projects that
were in a constant state of replanning due to plans being out of date
by the time they were completed. However, even projects using agile
development techniques usually must have some kind of longer range
plans that show customers the feasibility of delivery dates of a completed
product.
I do planning but often I don’t produce a plan document.
Is that consistent with my position of planning before plans. Absolutely.
I
only need to communicate the result of my planning as appropriate and
that may occur in many ways other than a written document. The essential
elements, to me, are well reasoned decisions that have buy-in from
all the appropriate stakeholders and a well thought out sequence of
actions. The act of planning communicates these decisions and actions.
In the next sections I want to first consider how to get the most
out of planning and then follow that with a discussion of constructing
plans.
2 PLANNING
Planning is often tedious and seldom quick. Planning involves deciding
the specifics concerning how some high level task will be performed.
Planning occurs prior to the actual action so that we have thought
through the entire sequence of actions prior to carrying out any of
the actions. Boehm and Turner characterize agile development as planning
driven rather than plan driven [Boehm 03]. Agile teams spend little
time communicating “the plan,” but conduct planning sessions
on a regular schedule.
Planning has its own rewards. Honest, it does. For one, you actually
have a chance of achieving your goal if you have planned how to achieve
it. For another, projects that use planning can often eliminate some
mistakes before they happen or at least before they become expensive
to fix. For example, beginning test planning in the very early stages
of a project often finds many of the requirements defects. This saves
a large percentage of the resources that would be required to fix the
defects later.
Planning is the most strategic activity in which we engage because
the very nature of planning causes us to look forward and to consider
options and goals. Planning before doing gives us the luxury of considering
the implications of each action which is much harder to do if we are
caught up in ongoing operations. An effective planning process contributes
directly to the success of sofware development by eliminating wasteful
actions that don’t contribute directly.
Planning Process
The act of planning requires longitudinal thinking and reveals logical
linkages. These processes help illuminate conceptual gaps and even
some incorrect assumptions so that the resulting plan will be an accurate
description of what has to be accomplished and how it can be accomplished.
Consider the following high-level planning activities:
Establish the high-level goal – The goal may be to create a
deliverable or accomplish some intermediate step toward completion
of the deliverable.
This activity should be revisited periodically so that planners can
remind themselves of the goal. This keeps the planning focused and
on track.
Scan the environment – This step identifies the forces that
will facilitate achievement of the goal and those forces that will
impede
efforts to achieve the goal. This step provides the essential context
and constraints that make the resulting plan realistic.
Analyze the high-level goal – The high-level goal must be converted
into an operational goal or set of goals. To me this is the most often
miss-handled step. The planners try to derive a concrete set of activities
for a high-level goal but the goal is not sufficiently specific to
allow measurement. The goal(s) in a good plan should be specific enough
to be measured and sufficiently broad to be strategically significant
accomplishments.
Develop strategies and tactics – For each operational goal,
a strategy needs to be adopted and tactics identified. I have previously
discussed the use of Porter’s Five Forces strategy development
approach in the context of developing a production strategy for a product
line [McGregor 04]. This technique guides the thought processes by
providing five standard forces that the strategy must resolve.
Develop schedules and assign responsibilities – Each activity
in the selected tactics is assigned and the schedule for its execution
is recorded. The success of the Toyota Production System (TPS) points
to the need for very specific assignments. Each activity should be
the responsibility of a specific person with other specific persons
assigned in backup and escalation roles.
This is a fairly standard set of steps. How we might make them more
efficient? Standardization and reuse. Many of the goals in a development
project are routine and occur in every development project and, in
fact, several times in the same project. Having a standard plan format
leads to a standardized planning process.
Decisions, Decisions, Decisions
The important aspect of planning that is often overlooked in a deliverable-driven
process is that a plan records important decisions about a project
or product. Seldom can these decisions be made by one person, and where
they can be, the person assigned to write the plan seldom has the knowledge
or authority to make them. This is not a matter of empowering engineers,
it is a matter of getting agreement among the set of engineers who
will be affected by the decision.
Decision making in software intensive system development is usually
a cooperative effort involving many complex trade-offs. Any one person
will have a single viewpoint and if only that person has input into
planning, the plan will only address issues from that perspective.
For example, if a process engineer is asked to write the development
plan, the process descriptions will be overlong, and perhaps overblown,
while important technical constraints may be vaguely referred to, if
addressed at all.
Ordinarily I would never advocate have a meeting of any kind. However,
a well-run planning session in which people are given materials ahead
of time along with a specific goal is often an efficient way to gather
input from all the stakeholders. The Product Line Systems Program at
the Software Engineering Institute (SEI) has shown that focused sessions
such as their Quality Attribute Workshop [Barbacci 03] or Production
Planning Workshop can be very effective in gathering the information,
establishing the context and making decisions that shape the eventual
plan. Each of these provide read-ahead materials, a structured agenda,
and managed interactions.
3 PLANS
The act of capturing decisions, made during planning, in writing
forces the planner to be more precise and concrete in the details.
I have
witnessed many incidents in which faults in programs or discrepancies
in documentation have been traced back to a developer’s vague
understanding of a task, which was never put in writing. Agile development
methods often counter this risk by having daily meetings in which such
inconsistencies might be caught.
Plans often follow a standard format. There are a number of IEEE
standards for specific types of plans. Some of them are shown in Table
1. (Notice
that IEEE discriminates between planning and plans in software quality
assurance.) Gary Chastek and I have provided a standard format for
a product line’s production plan [Chastek 02].
Standard forms support automation. The automation can range from
simple parameters to a document, such as variables in a Word document,
to
build scripts that assemble selected pieces based on choices made
at variation points in a product line architecture. Automation for
plans
reduces the effort for constructing the plan considerably.
| IEEE Std 730-1998, IEEE Standard for Software
Quality Assurance Plans |
| IEEE Std 730.1-1995, IEEE Guide for Software
Quality Assurance Planning |
| IEEE Std 828-1998, IEEE Standard for Software
Configuration Management Plans |
| IEEE Std 1058-1998, IEEE Standard for Software
Project Management Plans |
| IEEE Std 1059-1993, IEEE Guide for Software
Verification and Validation Plans |
|
Table 1 - IEEE plans
Figure 1 shows the standard outline of a production plan as defined
by Chastek and McGregor [Chastek 02]. We can create small purpose-built
tools that guide the completion of the standard plan. Figure 2 shows
the front screen of a wizard that guides the production planner through
completing the plan. The up front investment in the tool is amortized
over a number of plans that follow the same standard format.
| 1. |
Introduction |
| |
Production context |
| |
Audience |
| |
Qualifications |
| |
|
| 2. |
Strategic view of product development |
| |
Assumptions |
| |
Qualities |
| |
Products possible from available assets |
| |
Production strategy |
| |
|
| 3. |
Overview of available core assets |
| |
Basic inputs and dependencies |
| |
Variations |
| |
|
| 4. |
Detailed production process |
| |
|
| 5. |
Tailoring production plan to product-specific production
plan |
| |
Product production |
| |
|
| 6. |
Management information |
| |
Schedule |
| |
Production Resources |
| |
Bill of materials |
| |
Product-specific details |
| |
Metrics |
|
Figure 1 - Product Plan outline
4 EXAMPLE
Recently I have been working with the SEI on production planning.
One of the advantages of a software product line is that reuse goes
well
beyond reuse of code. By using commonality and variability analysis
decisions, constraints, and plans can be reused. Not only is this
efficient, it ensures a higher degree of consistency among products
and development efforts.
As part of my work on the Pedagogical Product Line for the SEI, I
produced a prototype for automating the creation of the production
plan. Figure
2 shows the front end of this system. The back end uses XVCL to encode
decision making logic [Zhang 04]. This logic selects from among a set
of predefined “chunks” that capture a particular decision.
While my approach assumes a closed set of decision outcomes, it is
possible to allow a more open ended system that allows the planner
to enter their own outcome.
XVCL provides a set of tags that support manipulation of text, whether
the source is a plan document or a piece of source code, The important
feature for our discussion of planning is that XVCL provides logic
operators that allow the encoding of decision making logic. Figure
3 shows a simple example of a selection statement. Each “option” is
a separate frame to process. The example shown corresponds to the first
set of choices shown in the interface shown in Figure 2. The complete
example can be seen in [McGregor 05].
The consideration that goes into developing this logic goes beyond
the thought necessary to write a plan in English. Incompleteness
is easier to spot because logical paths can be traced and the plan
generation
can be formally tested.

Figure 2 - Automated Production Planner

Figure 3 - XVCL fragment
5 SUMMARY
As you may guess from reading this article I have had some clients
lately who have written plans without planning first. The result
is first a sense of accomplishment that a task is finished followed
by perplexity when the plan fails. I once wrote a column titled “Let’s
Don’t and Say We Did.” Saying we have a plan when it
has not been thought through and vetted with the appropriate stakeholders
may satisfy some deliverable in a contract or process but it seldom
results in good plans or good products. Well conceived, well executed
plans can make a strategic difference for your organization. Automating
certain aspects of planning provides the same benefits as generating
code and other technical assets.
REFERENCES
[Barbacci 03] Mario Barbacci, Robert Ellison, Anthony J. Lattanze,
Judith A. Stafford, Charles B. Weinstock, William G. Wood. Quality
Attribute Workshops, Third Edition, CMU/SEI-2003-TR-016.
[Boehm 03] Barry Boehm and Richard Turner. Balancing Agility and
Discipline: A Guide for the Perplexed, Addison-Wesley, 2003.
[Chastek 02] Gary Chastek and John D. McGregor. Guidelines for Developing
a Product Line Production Plan, CMU/SEI-2002-TR-006, 2002.
[McGregor 04] John D. Mcgregor. Factors in Engineering Strategically
Significant Software Development Methods, Second Workshop on Method
Engineering for Object-oriented and Component-based Development, October
2004.
[McGregor 05] John D. McGregor. Preparing for Automatic Derivation
of Products in a Software Product Line, Software Engineering Institute,
CMU/SEI-2005-TR-017, 2005.
[Scwaber 02] Ken Schwaber and Mike Beedle. Agile Software Development
with Scrum, Prentice Hall, 2002.
[Zhang 04] Hongyu Zhang and Stan Jarzabek. XVCL: a mechanism for handling
variants in software product lines. Science of Computer Programming,
53(3), 381 – 407, 2004.
About the author
Dr. John D. McGregor is an associate
professor of computer science at Clemson University and a partner
in Luminary Software, a software engineering consulting firm.
His research interests include software product lines and component-base
software engineering. His latest book is A Practical Guide
to Testing Object-Oriented Software (Addison-Wesley 2001). Contact
him at johnmc@lumsoft.com. |