John D. McGregor, Clemson University and Luminary Software
LLC, U.S.A.
|
 |
COLUMN

PDF Version |
Abstract
Strategic goals are of no use if you can’t tell whether they
have been accomplished. A measurement program is an essential element
in the strategic arsenal. In this month’s issue of Strategic
Software Engineering, I will explore some issues about measurement
and effective strategic metrics. I will discuss some specific metrics
but also how to setup a measurement program that addresses your needs.
1 INTRODUCTION
I once sat through a presentation of the metrics group for a rather
large project. By the time the report was completed I knew how many
lines of code had been written so far, the number of defects detected,
the number of use cases written, and I had mentally drafted a column
(for another journal at that time). I was very grateful when the project
manager looked at the presenter and said, “yes, but how are we
doing?” No doubt, the report had given an accurate description
of the project but it had not provided any information that could be
used to afirm the present direction of the project or to make corrections
to that direction.
Descriptive metrics, which simply summarize a set
of measurements, are intended to describe “what is.” Descriptive
metrics can be useful to quickly give an overview of the current situation.
They can be made even more useful when used as a basis for comparison,
discovering trends, and summarizing large quantities of more detailed
measures. Descriptive metrics must usually be interpreted in the context
of some model of the ideal domain such as “All variables will
be private.”
Prescriptive metrics provide guidance for decision
making by producing results which convey an explicit value judgement.
Where a descriptive
metric might say “The current value is 12 lines of code per day”,
a prescriptive metric says “Programmer productivity improved
12%.” Prescriptive metrics are sometimes computed by combining
several measurements of descriptive metrics according to some formula.
Programmer productivity improvement would be computed by comparing
current productivity with some previous value.
One of the frustrations
for project managers is the need for historic data – benchmarks – that
can be used to interpret the meaning of descriptive measures or to
compute prescriptive metrics. Industry
standard benchmarks have not been widely used in software engineering
due to the complex nature of the context that affects the value that
is produced. However, some models, such as COCOMO [Boehm 00] are accompanied
by default values. There are so many factors that affect the qualities
of a software development process that the most effective metrics are
ones that measure your process now against your process previously.
Most metric programs begin by collecting descriptive measures and eventually
use these values to compute metrics that are useful in decision making.
Having
given Metrics 101, I will now focus on the strategic use of metrics
in software product production. I will discuss ways to define
effective metrics and to use the information provided by these measures
to improve product production. While I will specify a few metrics,
the most important contribution of this column will be to raise some
questions that lead you to define your own metrics.
2 GQM
GQM stands for the Goal-Question-Metric technique developed by Basili
[Basili 99] for defining metrics. Several brief industrial strength
examples of the technique are given at [Informit 05]. At a strategic
level, goal satisfaction is a primary driving force. Every strategic
metric begins with the need to track progress toward a specific goal.
Strategic Goals
Strategic is in the eye of the beholder. That
is, strategic refers to encompassing
some conceptual whole relative to the definer’s responsibilities. For
a CEO, strategic goals are those that address the entire organization.
For a project manager, strategic goals are those that address an entire
project, but these are tactical, narrower in scope,
from the perspective of the CEO.
Strategic by its nature also refers to a relatively longer
time period than tactical, which encompasses some subset of the whole
addressed by a strategic view. A time period that is considered long for
the project manager will be viewed as a much shorter time period for the CEO. Strategic
measures are less sensitive to short-term fluctuations and expose trends rather than incidents.
Tactical objectives often address some implementation of the strategy
intended to satisfy the strategic goals. Since a tactical objective
addresses a portion of a strategic goal it naturally has a much
shorter time horizon than the strategic goal. Tactical objectives provide
the short term reaction to longer term directions.
Tactical measures
are gathered from a more constrained population and over a shorter
time period than strategic measures. Progress
on the reduce
time to market goal can not be measured accurately until
several products have been delivered. The tactical objective reduce
time to productivity can
be measured after a few programmers have been trained which would
usually be a much shorter timeframe than delivering a set of
products.
Every manager should use a blend of long term, wide reaching
strategic goals and a second level of shorter term, more narrowly
focused tactical objectives, to guide their organization. Some
of the strategic
goals we have presented in previous columns include reduce
time-to-market, improved
productivity and improved quality.
Likewise, the manager should use a blend of strategic and tactical metrics
to monitor the organization.
The reduce time to market strategic goal
could lead a manager to adopt a strategy such as hire
more programmers. Tactical
objectives could then
be chosen to reduce time-to-productivity achieved
by speeding training
and using mentoring programs and to increase automation,
achieved by purchasing or crafting additional software tools. Corresponding
metrics should be defined to measure progress on these goals.
Applying GQM
The fundamental idea behind GQM is to maintain traceability from a goal
to the metrics that are intended to measure progress toward that goal. This
results in metrics that are more relevant, and more accurate. Essentially,
the process begins by taking each goal and identifying questions that, when
asked, would reveal what progress is being made toward accomplishing the
goal. Each question is then translated into attributes that, if measured,
would allow the manager to answer those questions. In many cases the results
of the measurements are filtered through a computation resulting in a metric
that answers the question. Figure 1 shows the chain from goal to question
to metric for the reduce time-to-market strategic goal.

Figure 1 - GQM chain of dependency
Metric Context
As with any measurement, metrics that will be compared must come from a common context. A personal example, when on a diet you should weigh at the same time of the day wearing similar clothes in order to compare weight over several days. For a software development organization the strategic context is defined by several attributes including:
- The development process – When the activities in the development process
are changed, the context changes. Previous measurements that relate to
the activities can no longer be compared to new measurements that are related
to a different set of activities. For example, many of the metrics used
to evaluate a traditional development process are not appropriate for an
agile development process. This affects process metrics.
- The design method – Structured design, object-oriented design, aspectual
design have different objectives. Even some very fundamental notions such
as modularity are viewed differently in these various approaches. This
certainly affects the definition of design metrics and some process metrics.
- The type of system – For example, in developing real-time software
a design that would be rated very highly by the metrics for an interactive
data entry system would be rated very low by the design metrics for real-time
software. This affects at least some product metrics.
- The personnel – Experienced developers produce more lines of code with
fewer defects than novices. Domain-experience is one part of that
experience factor. Loss of several domain experts will, if they are
replaced by less
domain experienced personnel, render previous time estimates useless.
This affects process metrics.
The scope of strategic metrics make them
vulnerable to very complex
and changing contexts.
Strategic Metrics Do’s and Don’ts
There are various lists of how to define effective metrics [Lermusiaux 05]. I will just touch on a few points.
Do update the context, and consequently the metrics, periodically. Goals
change and so does the organizational context. Include a review, and, if
necessary, a revision of the metrics with every review of the strategic goals
of the organization.
Consider some of the popular metrics about object-oriented
software development. One is depth of the inheritance hierarchy. This
metric was born early in the life of object technology. It is descriptive.
For a
particular design you get a 4 if there are three levels of children
under an abstract class. In certain design philosophies this was treated
as not
as good a design as one with a hierarchy of depth 2.
Some languages did, and maybe still do, impose a performance penalty on
deep hierarchies. However, recent implementations of most languages
have eliminated this penalty and some newer languages never had a penalty
at all. As a result
we see, in the Java libraries for example, very deep hierarchies that
work very well. Change in language implementation change the need for a
particular metric and its interpretation.
If one of the goals is reuse, the deeper the hierarchy
the better.
However, if one of the goals is more flexible and dynamically modifiable
software inheritance is not the best approach and the deeper the hierarchy
the less appropriate the design.The design philosophy is part of the
metric context.
Do not rely on a single measure. Strategic issues are complex. There is
usually no single attribute that will give a complete view of progress to
the
goal. Be certain that the questions asked cover all facets of the goal
and that
measures provide complete answers to questions.
Do recognize the limits
of the accuracy of the measurements. Attributes that describe strategic
goals are usually very high level. The accuracy of the measurements
will be affected
by the clarity and concreteness of the definition of the quantity to
be measured. Where possible encode the definition of the attribute
in a tool that automatically
performs the measurement.
Do account for the variation among measurements. A single
value is more representative of a group of measures if there is little difference
among the values. Simply reporting an average is not useful. Because almost
none of the actual measurements may have been close to that value. Reporting
the average and either a range of values or a variance allows more meaningful
interpretation. Strategic attributes are sufficiently encompassing that large
variations in values may be more of an issue than exactly what the values
are.
3 STRATEGIC METRICS
We now have a technique for defining metrics and some idea of what makes them strategic, so what are some strategic metrics? According to the earlier discussion, a metric is strategic if it covers the width of a manager’s interest and takes a long term view relative to the life of the activity. It is effective if it provides unambiguous guidance for decision making. Since strategic is relative I will address managers and developers separately. It is not my intention to prescribe a complete set of metrics. Use these as examples and use GQM to define the precise set that is appropriate for your organization.
Managers
Managers are usually interested in the two traditional categories of metrics: process and product. I have already mentioned some goals that managers have. Lets consider two: improve
product quality and make product production more efficient.
In order to evaluate improve product quality, I will use the definition
that quality is satisfaction of the requirements, but with the caveat that
those requirements include non-functional quality attributes [Bass 03].
Make
product production more efficient is very much dependent upon
the software development process used by the organization. The Software Engineering
Institute (SEI) has provided a strategic model for this in the Capability
Maturity Model
(CMM) [SEI 05]. I will defer to the large body of literature in this
area.
I will describe one type of strategic metric that actually addresses
both
these areas. In this case the goal under consideration is improve
the quality process. A strategic metric in this area would be the defect
live range.
This metric is not an easy one to compute but it certainly has strategic
importance.
This metric measures the length of time, in terms of the product development
life cycle, from a defect being injected into the product to the time
it is detected and repaired. Where the defect is detected can usually
be determined
very accurately. It is sometimes less clear where the defect was injected.
Typically some level of analysis will be required to determine this.
Table 1 shows a matrix in which the row signifies when a defect was
injected and
the column indictaes when the defect was detected and repaired. Figure
2 shows a graphical representation of the same information.
These values
can
be reduced to ranges by subtracting the index of the row from that
for the column. So the 20 defects injected in phase p1 and detected
in phase p1 have
a live range of zero phases because they did not escape the phase where
they were injected. We can then multiply by the number in the cell.
In this way
we could produce the average defect live range for design defects or
requirements defects. For p1 the computation is:

So the average requirements defect lives into the next phase, but most are
detected in the requirements phase. The assumption is that the smaller this
number, with a lower limit of zero, the better the quality assurance
process
since
the longer a defect lives the more costly it is to repair.
Table 1 - Inject to Detect Defect Ranges
| |
P1 |
P2 |
P3 |
... |
... |
Pn |
| P1 |
20 |
5 |
3 |
0 |
1 |
1 |
| P2 |
|
30 |
5 |
2 |
0 |
2 |
| P3 |
|
|
10 |
4 |
1 |
0 |
| ... |
|
|
|
5 |
1 |
1 |
| ... |
|
|
|
|
1 |
0 |
| Pn |
|
|
|
|
|
0 |

Figure 2 Defect Live Range
A second type of strategic metric for managers tracks actuals to predictions. For example, the manager may have used some cost-benefit prediction such as the SIMPLE model [Boeckle 04]. At specific milestones the actual costs and benefits to date are computed. These values are easy to compare if the milestones represent either a percentage of the time available for the project or an assumed percentage of the product is completed. Some measures such as return on investment can not be computed at milestones so stay with those measures that can be, such as costs.
Developers
For developers there are two types of strategic metrics. The first addresses the products they produce and their responsibility to their employer. The second addresses their professional growth and their responsibility to themselves.
I assume that over a strategic horizon every developer has a goal of improving
their productivity and quality. The Personal Software Process (PSP) provides
the developer with a forest of values that can be measured, see Table 2 [Humphrey
95]. Many of these are very detailed and address very specific actions taken
by the developer. These tactical metrics allow the developer to identify
specific improvements to make. I suggest that a strategic measure for a developer
is a more encompassing, less specific metric: iterations required
to achieve a build. This is similar to the process yield metric of PSP but I measure
through to product build while PSP stops at compilation and PSP measures
number of defects while I simply care about iterations. That is, how many
cycles does it take to get a finished piece of code? And is that number decreasing
over time?
Table 2 – Sample of PSP metrics
| Defect density |
Time per phase |
| Review rate |
Size of base code |
| Development time ratios |
Size of added code |
| Yield |
Size of deleted code |
| Defect removal leverage |
Size of new code intended for reuse |
My second assumption is that every developer has the long term goal of remaining
professionally current. GQM applies here as well. Most developers at least
set yearly goals as part of the company evaluation scheme. Some of us set even
longer term goals than that. When a developer sets their strategic professional
goals, they should apply GQM to define metrics that will measure satisfaction
of those goals.
Learn a new technology or attain a new certification are typical
strategic goals for personal growth. Lets consider learn a new technology.
One possible
question is “How many examples have you studied?” This leads to
a descriptive metric which is indicative but not definitive. A more productive
question might be “Can I develop a product using the same number
of iterations to build as with the existing technology?” When the answer is yes, I
feel that I have fully learned the new technology.
4 MEASUREMENT PROGRAMS
A measurement program collects and disseminates quantitative data for decision making. An organization that operates a measurement program develops a culture that expects decision making to be based on data. The program should produce a suite of metrics that addresses all of the goals, processes and organizational structures. Some of the metrics contribute to the computation of wider-ranging metrics at higher levels of the organization and some are intended for immediate consumption.
Why does CMM not include quantitative process management until Level 4?
Because it takes a certain maturity to consistently take best advantage of
this type of specific input. But that does not mean that organizations should
not begin to collect, review and react to quantitative data until then. By
the time you reach level 4 you should have sufficient historic data to understand
its importance and to be able to do historic comparisons.
When do I measure?
Measures should be collected periodically. There is no one period that
makes sense in all cases. I will give two answers.
- Some measures are applied at project milestones such as the end of the
first iteration or increment. Certain product-based measures only make
sense at times when a certain point in development is reached. Development
process-oriented
measures also are applied at milestone.
- Some management process-based measures are applied at regular calendar
intervals such as every quarter. Measures that are to be contrasted to annual
budgets or stockholder meetings are applied at these intervals.
How do I measure? Measurements need to be made in a structured manner that
ensures that the measures are giving correct answers and consistent answers.
- Take measurements at regular intervals but avoid periods of chaos.
I once asked an industrial training class, “How is it going?”,
as a casual opening remark. It turns out many of them had been given
30 days notice the previous day. Measuring their productivity that
day would
not have been a good idea. (Nor was asking how things were going!)
- Use a standard measuring instrument. At one time the yard was defined
as the distance from the nose to the tip of the finger of a member
of British royalty. Rather, use standardized questionnaires, formulas,
or
industry standard data definitions so that the measures are repeatable.
Do I need a metrics program if I am doing agile development? I think every
organization should have a metrics program even if the organization is currently
happy with their processes and products. Obviously an agile development project
needs an agile metrics program. It needs metrics that are oriented toward
individuals and that have a short time horizon. GQM provides a natural progression
to determine what should be measured regardless of the process model being
used.
5 SUMMARY
The most important, and most difficult, issue regarding a measurement program
is establishing a culture that respects and utilizes data in decision making.
The most relevant metrics will not provide any value if they are not consulted.
Ironically, the best way to establish this culture is to define relevant,
effective metrics that provide useful information. In my view this means
carefully choosing a small set of strategic metrics that can summarize information
that is too distributed for one person to experience personally. Periodically
measurements should be used to measure the costs and benefits of the measurement
program.
A Project DashBoard is a summary of current values for an essential set
of metrics the manager should be watching to understand the health of their
organization. This device works because it limits the manager to a small
set of metrics. It is effective because it makes it easy for the manager
to scan the values. And, since it is easy the manager might actually use
it. The DashBoard should contain strategic and tactical metrics and both
descriptive and prescriptive metrics. This blend provides comprehensive coverage
that provides useful information for decision making. REFERENCES
[Basili 99] V. R. Basili, L.C. Briand, and W. L. Melo. “A Unified
Framework for Coupling Measurement in Object-Oriented Systems”,
IEEE Trans. on Software Engineering, vol. 25, No. 1, (1999) 91-121.
[Bass 03] Len Bass, Paul Clements, and Rick Kazman. Software Architecture
in Practice, Second Edition, Addison-Wesley, 2003.
[Boeckle 04] Guenter
Boeckle, Paul Clements, John D. McGregor, Dirk Muthig and Klaus Schmid. “Computing
Return on Investment for Software Product Lines”, IEEE Software,
vol. 21, No. 3, May/June 2004.
[Boehm 00] Barry W. Boehm, Ellis Horowitz, Ray Madachy, Donald Reifer,
Bradford K. Clark, Bert Steece, A. Winsor Brown, Sunita Chulani, and
Chris Abts. Software Cost Estimation with COCOMO II, Prentice-Hall,
2000.
[Humphrey 95] Watts S. Humphrey. A Discipline for Software Engineering.
Addison-Wesley, 1995.
[Informit 05] http://www.informit.com/articles/article.asp?p=30306&seqNum=4
[Lermusiaux 05] Yves Lermusiaux. Characteristics of a Good Metric.
http://www.ilogos.com/en/expertviews/articles/strategic/20030709_YL.html.
[SEI 05] Capability Maturity Model, http://www.sei.cmu.edu/cmm/.
About the author
Dr. John D. McGregor is an associate professor of computer science at Clemson
University and a partner in Luminary Software, a software engineering consulting
firm. His research interests include software product lines and component-base
software engineering. His latest book is A Practical Guide to Testing Object-Oriented
Software (Addison-Wesley 2001). Contact him at johnmc@lumsoft.com.
Cite this column as follows: John D. McGregor: “Metrics",
in Journal of Object Technology, vol. 4, no. 2, March - April
2005, pp. 49-58 http://www.jot.fm/issues/issue_2005_03/column5
|